Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night we will be excavating the the pits for the Gifas boxes and grouted the slabs from Next to H&M

Tonight we will be laying the kerbing to the top of High Street, laying slabs to the central area & grouting to EWM. The Gifas boxes will be intalled
 
 
Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
 
We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info
 
We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Tuesday, 8 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night we lowered underground cables and raised all the tree pits up to the new levels.
 
Tonight we will be continuing excavating and laying kerbing and excavating for 2 electrical boxes to be installed.   

Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Monday, 7 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Tonight we will be excavating and lowering electric cables (working with Western Power) across the carriageway to allow the kerbs to be laid and manualy excavating for Gifas Electrical boxes to the central section.

 
Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
 
We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info
 
We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Friday, 4 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night the central kerbing was laid upto Next and the slabs laid upto the Crown Plaza entrance.

Tonight we will be completing the slabs in the vicinity of Crown Plaza and EWM and setting the covers and frames to the ironworks.
 

Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Thursday, 3 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night the kerbing was completed up to Fish Street and some pointing was carried out upto H&M.

Tonight we will be continuing with the kerbing and the laying of slabs.


Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Wednesday, 2 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Due to the heavy rain last night, progress was slowed with the works on the High Street.

The works we are planning to carryout tonight, consist of slab laying in the vicinity of Next and H&M, plus laying kerbs on the central kerb line.



Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.

Tuesday, 1 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

The works carried out last night on the High Street consisted of laying slabs from Next up to H&M, pointing a joint at the rear of the slabs next to All Saints Church and excavating trial holes for the central kerb line.

The works scheduled for tonight will consist of continued slab laying in the vicinity of H&M and Crown Plaza, plus start work on the central kerb line.



Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info