Friday, 4 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night the central kerbing was laid upto Next and the slabs laid upto the Crown Plaza entrance.

Tonight we will be completing the slabs in the vicinity of Crown Plaza and EWM and setting the covers and frames to the ironworks.
 

Our Public Liaison Officer for this scheme is Terry Godwin, Terry will be on site on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carryout these improvement works to the High Street.