Last night we installed the bollards at Elgar Statue, completed the grouting to the central area, moved the illuminated sign at Pump street and cut in the slabs.
Tonight we plan to install the gully oppisitr Pump Street, install benches and cycle stands and continue with the grouting.
Our Public Liason Officer for this scheme is Terry Godwin. He will be on site on a regular basis and will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
We will continue to update this blog on a daily basis (Monday-Friday) so please ensure you visit regularly for information on the progression of this scheme. Information on other roadworks throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info
We appreciate your patience and understanding whilst we carry out these improvement works to the High Street