Tonight we plan to complete the kerbing, lay Slabs to the Crown Plaza area, begine the installation of the bollards from Jack Wills to Fish Street. We also plan to grout where possible weather permitting.
Our Public Liason Officer for this scheme is Terry Godwin. Terry will be onsite on a regular basis and he will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
We will continue to update this blog on a daily basis (Monday to Friday), so please ensure you visit this blog regularly for information on the progression of this scheme. Information on our other roadworks throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info
We appreciate your patience and understanding whilst we carryout these improvement works to the High Street
No comments:
Post a Comment