Wednesday, 30 October 2013

Worcester High Street Improvement Scheme - (Pump Street to Elgar Statue)

Last night we installed and grouted in all bollard cases, installed the gully opposite Fish Street and carried out more grouting.

Tonight we plan to install benches, excavate block paving to the carriageway and continue with the grouting.


Our Public Liason Officer for this scheme is Terry Godwin. He will be on site on a regular basis and will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday-Friday) so please ensure you visit regularly for information on the progression of this scheme. Information on other roadworks throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

We appreciate your patience and understanding whilst we carry out these improvement works to the High Street